at completion duration issue

U
umit timu 👤 Member for 10 years 1 month

Hi Folks

Im importing same xer file into enterprise and into standalone version of p6

Im getting different dates&floats when scheduling with retained logic

 

when investigating reason, i saw that at completion durations are different for some in-progress activities , but all settings are same on both platform. I couldnt find out why

 

Any ideas?

Z
Zoltan Palffy 👤 Member for 16 years 11 months

2 possibilities 

1. go to edit users preference look a the time units and look at the Hours per Time Period.

2. it is using the gloabl calendar instead of a project calendar and the two global calendars are different. 