Im importing same xer file into enterprise and into standalone version of p6
Im getting different dates&floats when scheduling with retained logic
when investigating reason, i saw that at completion durations are different for some in-progress activities , but all settings are same on both platform. I couldnt find out why
Any ideas?
2 possibilities
1. go to edit users preference look a the time units and look at the Hours per Time Period.
2. it is using the gloabl calendar instead of a project calendar and the two global calendars are different.