When I tried to import Excel file into Primavera P6 release 7, the last screen for importing (select the project from P6 you would like to import the Excel file to it) did not show any projects to be selected.
I guess this could be happened due to limited rights or OBS/EPS organizing, I tried but could not reach out how to solve it
any suggestion to solve it.
Sagar create a new post do not steal someone elses thread.
Hi Zoltan,
Can you help me to reply my below mentioned queries.
01) How to add Two primary Resources in P6 like I want General Worker & Skilled Worker as a Primary Resource but its only available one for each activity.
02) How to view Critical path Diagram as my management asking for that.
03) How to put Actual manhours in P6 against each activity.
04) How to print report for Planned vs earned vs actual manhour report in P6.
Thanks
Sagar Hassan
Sagar create a new post do not steal someone elses thread.
Hi Zoltan,
Can you help me to reply my below mentioned queries.
01) How to add Two primary Resources in P6 like I want General Worker & Skilled Worker as a Primary Resource but its only available one for each activity.
02) How to view Critical path Diagram as my management asking for that.
03) How to put Actual manhours in P6 against each activity.
04) How to print report for Planned vs earned vs actual manhour report in P6.
Thanks
Sagar Hassan
Sure I click in the lower right hand corner, but still have the problem. the problem look like it comes from the rights, but which rights I should have to manage to do this.
make sure you have the rights then click in the lower rigth hand conere where the 3 little dots are