Budgeted Units-Export to Excel and Import

K
Kannan CP 👤 Member for 18 years

Hi All,

I was trying to modify the budgeted units, by exporting it to excel and import back the modified values. Resource and units are set for all activities.

The issue is that in the exported excel file the sheet for resource assignment(TASKRSRC) is having only the heading, no details of the acivity, dates, budgeted units etc (blank cells).

Is any settings to be changed to have it in the sheet.

Thanks

BR

Kannan

Z
Zoltan Palffy 👤 Member for 16 years 11 months

make sure to modfy the export and select the budgeted units

also when exporting select resources and resource assignments

then whne importing only select resource assignments so that you do not duplicate the resource. 

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts