Hi All,
I was trying to modify the budgeted units, by exporting it to excel and import back the modified values. Resource and units are set for all activities.
The issue is that in the exported excel file the sheet for resource assignment(TASKRSRC) is having only the heading, no details of the acivity, dates, budgeted units etc (blank cells).
Is any settings to be changed to have it in the sheet.
Thanks
BR
Kannan
glad I could help
Thanks Zoltan...
make sure to modfy the export and select the budgeted units
also when exporting select resources and resource assignments
then whne importing only select resource assignments so that you do not duplicate the resource.