P6 Calender Time Periods for Different Work Hours

I want to make 3 different calanders for a project which needs to be 8hrs/5day working, 12 Hrs/6day working and 24hrs/7day working. In the "Time Periods" section of each calander what values i should use for Hours/Day, Hours/Week, Hours/Month and Hours/year for each calendar? In the Global calader available on our system it is showning same values for all type of calenders. Is this the correct approch? 