I would like to know the Construction activities in Tank Construction " Fuel Storage Tank - Fixed Cone" . Its a 10000 BPD Tank.
I have listed dow the activities in the sequence of Construction but please let me know if anymore details need to be added and monitored
Tank Civil Foundation
- Tank Foundation Excavation and compaction
- Blinding Concrete
- Form and Steel Work
- Concrete Pouring
- Soil Fill and Compaction
Tank Bottom
- Bottom Plates Installation
- Bottom Plate - Coating
Tank Shell
- Shell Plate Installation
- Shell - Nozzle and Manway Installation
- Shell - Final Coating
Tank Roof
- Roof - Center Deck Plate Installation
- Roof - Drainage Piping
- Roof - Final Coating
Tank Acessories and Fire Fighting
- Internal Accessories
- External Accessories
- Foam Piping Installation
- Final Coating
Can anyone let me know the manpower required to do the work.
Thanks
Jithin
Hi Jithin
Depends what it is holding. You need different coatings for different liquids. But you will need inside and outside coating.
Best regards
Mike Testro
Thanks Mike,
"So they made it straight". Poor guys took a lot of effort ;)
Mike its a total curved tank - so we would have to do 1 Internal Coating and 1 External Coating ?
The Tank dia is 14 M and Height is 10 M.
Thanks
Jithin
Hi Jithin
You can't do the bottom coating until you have welded the top and coat the whole tank.
If it is a circular welded structure you need internal bracing to prevent wind colapse until the roof is fixed and completes the structure.
You need an access panel for the internal work which is then welded shut before final coating and to get the bracing out.
I recall a precurved steel tank in Iraq for a village water supply. The welders arrived on site and the headman proudly declared. "Your steel was bent when it arrived but we managed to straighten it out for you."
Best regards
Mike Testro