We claimed Variation Works from client , But Can we claim loss of productivity due to impact of variation order on original scope??
loss of productivity due to impact of variation order on original scope
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Hi Manjar,
You need to haev aunit rate for ur PErsonals both Direct and Indirect in Contract but if you dont have you need to provide a unit rate table officially.
On this basis you need to prepare the variation order including all the cost Direct Manpower Indirect Manpower , Equipments used and Material.
The Direct manpower should be based on productivity which will give you the duration which will be based on how many people you can load to do that work. So if the Client is convinced he would approve the V.O/C.O.
Thanks
Jithin
Thanks Mike,
For variation order client will pay additional quantity , Impact of this VO on original scope , we can claim extention of time claim (Indirects Cost) but Directs manpower cost will be remain un-claimed - How we will claim additional direct manhours loss??
Hi Md
Yes you can but it would be difficult to prove and calculate accurately.
Let me have more details and I will try to assist further.
Best regards
Mike Testro