Airport Construction schedule

Member for

16 years 3 months

there is a lot to consider

Member for

17 years 11 months

Thanks Zoltan for your points 

 

I am checking the documents and requirements and will keep attention to your points 

appreciated 

 

BR

Alaa 

Member for

16 years 3 months

is this a new airport or a renovation of an existing airport ?

is there road work ramp work enplaning and deplaning ? do you have to keep these active during construction ?

is there a phasing plan ?

how many gates can you take down at a time ?

are you building any additinal runways ?

do you need swing spaces for exisrting tenenats ?

are you building a additinonal fuel tank farm ?

are you installing a gylcol recovery system ?

are you building a de-icing area ?

are you installing in ground fuel tanks at the gates ?

is there taxiway work ?

is there runway work ?

is there loading dock work  ?

is there air traffiic control tower wok as well as ground control tower work ?

how long does it take for construction personell to go through the badging progess to get AOA access ?

how are you going to get the craft onto the AOA area ? bus ?

are there seperate gates for the craft as opposed to airport employees ? 

are you bringing in concrete or do you have an onsite batch plant ?

do you have a deciated haul road through the airport as well as a stock pile area ?

are you working in an international arrivals area if so do your people need to be finger printed ?

shall I go on ?