Baseline Critical Path

Hi MSapiens/Planners,

I'm working on an MS Project file for quite sometime. It has got a baseline that was made long ago. Now, i want to see the critical path in that baseline. Can someone suggest me on sorting this out, using either custom filters or custom fields or any other possible means.

 

Thanks in advance.

Regards,

Siddharth

T
Tom Boyle 👤 Member for 19 years 6 months

Sorry Siddharth,

"Set Baseline" in MSP stores task and resource information, but not logic/relationships or float.  Since it is not possible to recover any logic from a stored baseline, you can't recover the baseline critical path.  Best practice is to save a separate mpp file of the baseline project.

Good luck, tom

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts