check any activity types that are LOE any LOE activities with resource MUST have a resource CURVE assigned to them or they will be stacked at the first day of the data date.
My guess is that the resource asignment record has a duration. And if it has, it overrides the activity duration. You can display the duration fields that apply to the individual resource asignment recorn n the "Resource" tab of the Activity Details lower layout by right-clicking on the existing column headings within that tab and "customise".
My guess is that the resource asignment record has a duration. And if it has, it overrides the activity duration. You can display the duration fields that apply to the individual resource asignment recorn n the "Resource" tab of the Activity Details lower layout by right-clicking on the existing column headings within that tab and "customise".
Member for
16 years 3 monthscheck any activity types that
check any activity types that are LOE any LOE activities with resource MUST have a resource CURVE assigned to them or they will be stacked at the first day of the data date.
Member for
18 yearschek the planned dates for
chek the planned dates for the activity
resource distribution is based on planned duration
Member for
21 yearsMy guess is that the resource
My guess is that the resource asignment record has a duration. And if it has, it overrides the activity duration. You can display the duration fields that apply to the individual resource asignment recorn n the "Resource" tab of the Activity Details lower layout by right-clicking on the existing column headings within that tab and "customise".
Member for
21 yearsMy guess is that the resource
My guess is that the resource asignment record has a duration. And if it has, it overrides the activity duration. You can display the duration fields that apply to the individual resource asignment recorn n the "Resource" tab of the Activity Details lower layout by right-clicking on the existing column headings within that tab and "customise".