Resource usage profile chart not displaying correctly?

Dear all,

sorry i am newbie in P6 and just doing some self study.

i am having some prblems with regards displaying the actual resouces used in my project. i have assigned the planned and actual resources on each activity but when looking ant the resource usage profile chart, all the actual resources are stacking up only on the first month? I dont know if I am doing it wrong or what?

Please help.

Thanks Alot in advance.

 

[[wysiwyg_imageupload:4452:]]

Z
Zoltan Palffy 👤 Member for 16 years 10 months

if these are LOEs or even not you can add a curve to the resouce for then to distrubute. If there in no curve assigned then the distrubuition should be linear. If they are LOE activites then they MUST have a curve assigned to the activity or you will get this spike

D
David Kelly 👤 Member for 21 years 7 months

Gosh...... this looks as simple as the progress has been added, but the data date not advanced?

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts