Resource Assigning

Usually, Project manager or Site Safety are on site from the start of project. we make a resource for Project manager. how can we assign this resource to activiteis? should i add it for all activiteis?  

Z
Zoltan Palffy 👤 Member for 16 years 10 months

as VAl said create a new activity call it what you want for the activity type make it a level of effort

make its predecessor a ss relationship to the very first activty in the schedule.

make its successor a FF relationship to the last activity in the schedule

assign a resource to the LOE activity

make sure to ASSIGN A RESOURCE CURVE to the Level of effort activity or the total manhours or cost for that resouce will be distributed only on the 1st day of that activity.  

M
Mujtaba Salehi 👤 Member for 9 years 8 months

Thanks for your Information. 

how about its complition percentange? i mean, according to which items should i put the percentage? 

M
Mujtaba Salehi 👤 Member for 9 years 8 months

Thanks for your Information. 

how about its complition percentange? i mean, according to which items should i put the percentage? 

V
Vladimir Liberzon 👤 Member for 25 years 4 months

Create LOE (hammock) activity that lasts from the site work start to site work finish and assign project manager, site safety and others who shall be on site all the time there, not on project activities that shall be done by project workers. 

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts