According to the common planning Practice, Earned Manhours = Actual Progress % " Monthly or Weekly " X Planned Manhours for the same scale and same period.
It is an indication, how much you must spend from your budgeted Mhrs at that achived Actual progress.
The earned manhour is the project original estimate. The actual manhour is the final cost of the project. Again, refer to the "tea cup" example: if the two men expend 350 to wash the tea cup and report 100%, then, the total project cost is 350 hours, while the original estimate for the project is 100 hours. I hope this makes sense.
Thanks for your excellent example, which make the difference very clearly.Also Could I consider that the actual manhour is to the project duration while the earned manhour is to Project cost,is this right?
You have estimated that washing a tea cup will take 10 hours. You have two men to wash the tea cup. They finish their shift and report 10% progress after booking 2 hours for the job.
2 hours is the actual hours, 1 hour (10% of 10 hours) is the earned manhour. I hope this helps.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi just wondering if we cant find out the current % progress or some alternative scale is used how do we find out the earned manhour
According to the common planning Practice, Earned Manhours = Actual Progress % " Monthly or Weekly " X Planned Manhours for the same scale and same period.
It is an indication, how much you must spend from your budgeted Mhrs at that achived Actual progress.
Olike:
Now its clear to me for these two velues, thanks again.I will consult to you if there is any question, please kindly assist me .
Xiangbo
Bo,
In simple terms;
The earned manhour is the project original estimate. The actual manhour is the final cost of the project. Again, refer to the "tea cup" example: if the two men expend 350 to wash the tea cup and report 100%, then, the total project cost is 350 hours, while the original estimate for the project is 100 hours. I hope this makes sense.
Cheers
Ifeanyi
Olike:
Thanks for your excellent example, which make the difference very clearly.Also Could I consider that the actual manhour is to the project duration while the earned manhour is to Project cost,is this right?
Olike
Good and simple way to differentiate between actual estimated man-hours
Hi Bo,
Consider this scenario:
You have estimated that washing a tea cup will take 10 hours. You have two men to wash the tea cup. They finish their shift and report 10% progress after booking 2 hours for the job.
2 hours is the actual hours, 1 hour (10% of 10 hours) is the earned manhour. I hope this helps.
Ifeanyi