Lag ,Total Float and Duration

Dear Family Members

What is the maximum and minimum Lag allowed in a program??

What is the maximum Activity duration can be allowed in a program??

What is the maximum and total float allowed in a program ??

 

Regards

Arun.V

R
Rafael Davila 👤 Member for 22 years 3 months

There are no such thing as a universal rules for planning, the rules shall be used only as a guide/warning on possible errors but not to define them as definitive error. Some of these rules might prevent you from creating better models.



Say concrete placing activity takes 6 hours but curing shall start after the 4th hour; there is a necessary lag that is more than 50% the duration of predecessor. You can bypass such 50% requirement if model lag as an activity.



Say an activity takes 3 months, common in linear jobs; if you split the activity into separate activities then resource leveling might spread them apart instead of keeping the activity contiguous.



Float is a calculation, if the software can do the right calculation and the model is good it will be whatever it comes to be.

K
Kannan CP 👤 Member for 17 years 11 months

Hi Arun,

1. For SS+ Lag, the lag should not be more than half of  the predecessor duration. Always try to avoid FS+Lag.

2. Try to limit the construction activities in 21 days, to monitor & control it properly.

3. Total Float depends on the proper logic in the programme.

 

BR

Kannan

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts