I have create a new project on 18th Aug with start date as 01st Aug. But, while creating the activities the start date by default is getting picked as 18th aug which is the data date. I want project start date (01st Aug) as the default start date for all activities. Could anybody guide me on how to achieve it?.
Default activity start date
Forum Sponsor
Top Posters
Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
go to PROJECTS
highlight you project
in the dates tab
set the start date and data date to august 1, 2016
David Kelly, Thanks.... it worked
Schedule the project and pick a data date which is the default early start date
constraint/actual the date, 01 Aug. alternatively, use as data date.
constraint/actual the date, 01 Aug. alternatively, use as data date.