Activity Duration

R
Raf Many 👤 Member for 9 years 10 months

Hi,

I have assigned manhours in the work column but the activity durations keep changing when I change the manhr value, how can I avoid changing activity duration?

P
Philip Day 👤 Member for 9 years 10 months

Hi Raf,

 

There is an unbreakable link in Automatically Scheduled tasks. So if you change any of these parameters after you have initially created the Task, it will affect the others.

 

If you change the Task Type to: Manually Scheduled. Make the Required changes and then remember to change back to Automatically Scheduled, you should find that you were able to change just the field expected, without breaking anything else.

 

Did this solve your problem?

Kind regards,

Phil

R
Raf Many 👤 Member for 9 years 10 months

Thanks

One more question;

when I change the activity duration the manhrs assigned change automatically, how can I avoid this?

T
Tom Boyle 👤 Member for 19 years 6 months

Raf,

Change the Task type from Fixed Units (the default) to Fixed Duration.

Good luck, tom

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts