Dear Members;
I need some tips regarding budgeted labor unit in P6 schedule;
Case:
I have a construction project with only one resource loaded (labour) and its assigned to all the activities with the budgeted labour units as per quantity of each activity, now how I can determine the percentage complete at WBS level as P6 calculate the Percentage complete with Budgeted Cost at WBS level.
Regards;
Siddiq
Deleted posted twice
Thanks David for your reply..
If you got some time i will send you the XER file and you can take a look at that...
Actually the program is made by other planner but now iam supposed to update it and get the status..But when i put activity % to the program nothing is changed at the WBS level...Hope you can understand the case with my broken english.This is my Email ID [email protected] if you send me a test mail i will send you the XER
Siddiq.
siddiq,
You must assign a cost to the resource, as P6's "Performance % complete" only rolls-up cost, not quantity. Of course if every resource is priced at $1.00 per unit then effectively they are the same thing. The % compete value you want is Performance % complete for the current schedule ( effectively BCWP) and from the baseline Schedule % complete (effectively BCWS)