Hi !!
I want to make a calendar in MSP 2013 for which I copied the 24 hrs shift.
Now using exceptions I entered the 4 national holidays which went fine.
I marked all the sundays as Off. Now we have a shift change / off day every 15 days or on the alternate sundays.
Can I do that using some command or I have to select every alternate sunday manually for the project duration ??
I did it using the exceptions tab
made an exception called "Alternate Sunday"
Then click - details; Non-Working radio button is selected &
used the recurrence pattern.
If any other method is there plz let me know.