Which Primavera P6 Percent Complete Type to Use?

Primavera P6 has three different ways to track schedule progress. Here we explore the best applications for each type  http://ow.ly/Mxpq302V5DS

D
David Kelly 👤 Member for 21 years 7 months

Simple:

 

If you are an Owner who employs contractors,  you use Duration

If you are one of those contractors, you use Physical (the only way to keep Earned Value, Remaining Duration, and Remaining units independent)

If you are the victim of a cruel medical experiment, you use Units

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts