Hi David - Love it!
Simple:
If you are an Owner who employs contractors, you use Duration
If you are one of those contractors, you use Physical (the only way to keep Earned Value, Remaining Duration, and Remaining units independent)
If you are the victim of a cruel medical experiment, you use Units