Hi Everyone, I would like to share with you construction civil works productivity rates, I found this file very useful, what you think?
Productivity Rates for Tilling Size. (Cms)LocationAreaManpowerProduction RateRemarks (Sqm. Per day) 30 X 30FloorKitchen1 Mason, 1 Helper14Residential Area by Sub-Contractor30 X 30Floor with patternCorridor1 Helper, 2 Masons10Residential Area by Sub-Contractor40 X 40FloorBed room1 Mason, 1 Helper22-25Residential Area by Sub-Contractor20 X 20FloorStore (small area)1 Mason, 1 Helper 10Residential Area by Sub-Contractor30 X 60FloorBathroom2 Mason, 1 Helper6Residential Area by Sub-Contractor30 X 30Floor + WallBathroom2 Mason, 1 Helper5 10 X 10WallKitchen1 Mason, 1 Helper8-9Residential Area by Sub-Contractor30 X 60WallCorridor1 Mason, 1 Helper14-15Residential Area by Sub-Contractor30 X 30WallBathroom2 Mason, 1 Helper7Residential Area by Sub-Contractor Residential Area by Sub-ContractorNotes: 1. 1 Day = 10 hrs. 2. Gang Size: 1 Mason + 1 Helper for Kitchen and Bedroom. 2 Mason + 1 Helper for Bathroom.
Thanks Hany