Remaining Late Units before Data Date

Hi everyone,

I was updating the progress. Wanted to extract actual & remaining labour units from primavera P6 R8.2in order to create Actual & Forecast curves.

I checked the forums, tried some options like:

- Negative Float - I have none

- Constraints - There are no constraints in the schedule, there is one Project constraint where you have to put Must Finish by x date. That comes after couple of months Early Finish Date.

My schedule still has Cumulative Remaining Late Units.

What do I do? Any advice would be appreciated.

I
Islam Thabet 👤 Member for 11 years

 

THEN COPY FROM XER TO EXCEL DATA SHEET

I hope you find the right answer in this Pic.

[[wysiwyg_imageupload:4345:]]

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts