in P6 R8.3.6, I want to move various labour resources on various activities to other existing activities. Some of the resources have been wrongly allocated, others need to move to a different time period.
I want to move the resources with the associated Resource Assignment UDF's.
Is there a way that I can drop and drag the resource and assigned codes from one activity to another in Resource Assignment Tab (similar to task drop and drag in Activities table)?
Or can I do it some other way - drop and drag/ copy & paste?
Plan B is to reassign using excel export/import (create and delete) - or is this the only way to do it without SQL access?
Thanks
Zoltan
Appreciate the quick reply. Will proceed on this basis.
Would be nice to have in Primavera 9.
Zoltan
Appreciate the quick reply. Will proceed on this basis.
Would be nice to have in Primavera 9.
plan B is your answer