Resource Curves issues

When using a resouce curves to assign cost to the very end of an eactivtiy, the cost is not always in the correct month if end of the activity is in the first few days of the month,

I assume that when creating a curve it doesnt actually have it as 100% at the end rather between 95%-100% hence the cost not appearing in the right month.

Can anyone explain a way of having the budgeted costs on the very last day of activity in resource assignemnt view?

Thanks

R
Rafael Davila 👤 Member for 22 years 3 months

I am not a Primavera P6 user but at times receive P6 XER files to be transferred to my software so I do not know all the implications of the following suggestion with regard to resource leveling. I receive the XER files but do not have P6.

Try resource lag and resource duration, for example if activity duration is 10 days use 9 days for resource lag and one day for resource duration. It should work well for fixed duration activities as long as you do not make changes to total activity duration. Workarounds should always be of last resort. 

https://www.youtube.com/watch?v=KukSYuCFAS8

Good Luck

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts