Apply Actuals/Update Progress

What is the difference between Apply Actuals and Update Progress, except that you can update more than one project in Apply Actuals dialog box?

Thanks,

Mick

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Milovan,

if you read Paul Harris books, you will learn that Apply Actuals was available in former versions of the software before Update Progress

Apply Actuals can only be used when the corresponding option has been checked either at resource or activity level; therefore, you are able to select which activities and / or resources will be updated

Apply Actuals also allows the user to update a project by applying the actual hours entered in the timesheets.

Paul is not really in favor of Apply Actuals

Alexandre

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts