Microsoft Project calculates percentage completion based on duration of the task. Hence Main task reveals the percentage completion based on the duration of subtasks. In reality, duration is not the deciding factor to calculate the project's overall percentage completion. Some activities takes more time, but its contribution to the project's overall percentage completion may be less. Some activities may take less time, but its contribution to the project's overall percentage completion may be more. Hence I would like to assign a weightage to each activity and wants Microsoft project to calculate the overall project percentage completion based on the weightage assigned and percentage completion updated.
Can someone explain how to assign the weightage on our own to each task for measuring the project overall progress percentage.
Regards,
Jaga
Nice post by Mr. Abdul Samad.. ! Keep up...!
Dear Abdul Samed,
I followed your steps by using the custome field to calculate the formula for the column weighted progress and it is ok, my question how to show this column in the graph as it is the indicator i am using to calculate the progress of the project?
Best,
Muataz
Dear Abdul Samed,
I followed your steps by using the custome field to calculate the formula for the column weighted progress and it is ok, my question how to show this column in the graph as it is the indicator i am using to calculate the progress of the project?
Best,
Muataz
Dear Jaga,
It is very usefll instruction but if you share with me formla for the same is highly appriciated.
Also if i would use % Completion inplace of phycical complition it is ok for logic.
Regards,
Sandeep
Jaga,
you create a new column of type Number.
Assume that you want to measure the project progress with 1000 points( weightage points or simply weightage). The project then will be completed if 1000 points are achived by the project. How to distribute these points against activities is based on the many factors. Some companies distribute these points in proportion to the budget allocated for each activity. Some companies distribute these points based on the importance or criticality of the activities. Some people do it based on the durations of activities and some others based on combination of all these.
Any way, distribute these weightage points in this column against all significant activities totalling 1000 points for the entire project.
Insert another standard column called Physical Progress %. Enter the physical progress achieved against all the activities as of a particulare cut off date( Data Date/ Status Date).
Have another column of type Number, and name it as Weighted Progrss. Put a formula for this column to multiple the physical progress % with the weightage points. This value contribute the real progress of the activity towards the project progress. The sum of all the values in the Weighted Progress column can be considered as the over all progress of the progress. When the sum of values in this column becomes 1000, the project is completed.
For example, if the sum of the pints in Wighted Progress column is 750, the project is progressed 75 %.
Mail me if you need more info: [email protected]
Jaga,
If you resource the schedule and progress it using the % work complete field then the summarised (% work completed) totals will be weighted.
D
Trevor, I like your bricklaying example -- with your permish, I may adapt it for my undergraduate class.
An example I use is that we are building a highway 100 miles ling and have completed 90 miles:
In project management, almost any yardstick of measurement is going to have potential to distort and to be "gamed", to a greater or lesser extent, due to the fact that:
Some general comments about progress management:
If one wants to use earned value based on cost or resource use to measure schedule performance, it is crucial to use a completely different EV baseline (BCWS or PV) for schedule:
Fraternally in project management,
Steve the Bajan
.
You have said that you want to measure something called "overall project percentage completion". What is it? Is it something that you can measure or calculate? What is the numerator and denominator?
If you have 2 tasks, each to lay 10000 bricks, which are estimated to take 10 days each, and the total duration is 20 days, and each task costs $4000 for the person and $10000 for the materials, after 6 days you have a certain number of bricks laid in the first task, what is the "overall project percentage completion" ?
Hi,
Another way is to attribute M/H to work field and then display percentage of work. This way MSProject calculates and displays correct weighted progress on summarys.
BR
JMFrade
Miimoune,
I don't agree with your statement that planning software is good only for calculating dates. Good software is a tool for decision making and most management decisions are based not only on time, but also on cost, scope and risk considerations. If softwate just calculates dates it is useless.
Jaga
i have a couple of files that you may find interesting, it is about process for project controls ( Progress, reporting time sheet, scope and such) my advice to you let the planning software do what they are best in doing, time management, calculating dates.
the tools are generic, they works with any planning software.
https://www.box.net/s/ryfxdtnnyhz7qpufgp5l
regards
mimoune djouallah