S-Curves in Primavera

Member for

15 years

Hey

Member for

14 years 11 months

Thanks Waseem,

 

But what I want is to timely display or graph percent completions not for individual activities or resources only...but as a whole project...like 10%-1stMonth,15%-2ndmonth, 40%-3rdmonth.....etc... just this simple info I am exploring to display...And I start to think that this is impossible in P6 without additional calcs. and integration with other software such as excel. right? I wish a lot to be wrong and that someone show it to me.

Member for

20 years 11 months

Hi Cenk,

did you added the resource for the cost, if yes, click on the Resource Usage Profile, select the resource for the cost and it should display the required profile, you will need to do some modification on Res/Role Usage Profile options, select the At completion Cost and under Show select the Total Cumulative Curve........

hope this helps and am sure there are so many threads on this topic, advice to go through and it should help.

 

Cheers!

 

Waseem Saber

Member for

14 years 11 months

-

Member for

14 years 11 months

Hi friends,

 

How can I display planned period percent of completions for whole project in a spreadsheet form and as an s-curve?

I would appreciate your guidance.. But I kindly ask you to be precise when guiding..

my email is: prjmngr<at>mail.ru

 

thanks in advance

cenk

Member for

18 years 10 months

Hi,

I am interested in your excel sheet.

I will send you a pm.

regards

JW

Member for

21 years 8 months

Hi D Artagnan,

Came across with your posting in the Planning Planet wrt Excel connecting to P6 database to generate s-curve and cash flows.

I'm interested with it and wish if you could kindly email to "amo007@streamyx.com".

Thanks & Cheers;

Member for

21 years 8 months

Hi D Artagnan,

Came across with your posting in the Planning Planet wrt Excel connecting to P6 database to generate s-curve and cash flows.

I'm interested with it and wish if you could kindly email to "amo007@streamyx.com".

Thanks & Cheers;

Member for

16 years 7 months

Athar,



Please request this by sending D Artagnan a PM (private message), rather than giving out your email. We discourage people distributing email addresses here, as there are spammers and scammers who have used this site in the past.



To send a pm, click on the blue envelope next to D Artagnan’s name below.



Cheers,



Gary

Member for

16 years 7 months

Dear

Please send me that excel program for S-Curve

*email removed by Gary W*



regards

Member for

17 years 1 month

i designed an excel sheet that connects p6 database to access to generate s-curve and cash flow. if interested you can send me pm.

Member for

20 years

Hello Ersin;



If u are not going to assign resources on your schedule, u can do this:



Create a fictitious resource (eg: S-Curve);

Stipulate weights for all activities (using excel);

Assign resource S-Curve in all activities using weight for budget unit;

eg: Stipulate 1.000.000 as 100% of your project, so u it eliminates the use of much decimal (eg: 0,000003 budget);



If u assign only this resource, u can create a S-Curve direct from Primavera. If u asign any other resource, go to Assignments, create a lay-out showing Cum Budget and Cum Actual and use a filter "resource is equal to S-Curve". Than, copy and paste in excel and create a curve;



Hope it helps;



Regards.


Member for

20 years 10 months

You can make S-Curves in Primavera in Units or cost by adding all resources and cost to the activities and you can see this S-Curves in Primavera by display activity usage profile from tool bar . also you can see earned value curve and S-Curves also from tracking layout.

ENG. Said tahoon