Dear All,

I have already assigned a baseline and have been updating site progress every week.Although I found that project delay doesn't change when I do updation.I checked the driving activities in longest path, then I found that one very important activity is not driving rest of the actvities.I want to make that actvity as drving activity.Please someone help me to change that activity as driving activity.

Thank you

Moh

I
Irfan Khan 👤 Member for 16 years 10 months

is that activity is in your critical chain ?

change the logic & try to make a proper relationship through that your activity will drive all the successor activities.

 

 

 

Z
Zoltan Palffy 👤 Member for 16 years 11 months

you can't MAKE a activity driving the logic and durations deterrmine that do you have a project must finish by date assigned to the project  ?

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts