I'm new to primavera.When I schedule the project after updating, Performance % complete is higher than schedule % complete. Although Anticipated finish date is higher than baseline finish date. Can someone explain me the reason as soon as possible because I have to send weekly report to consultant.They would ask the reason at me.Please
Thank you
Mohamed
Dear Mohamed,
This could be because you are much advanced in the non critical path activities and delayed in the critical path activities.
The earned value calculation will reflect this.
Best Regards
Kannan
so you mean that fnish date is LATER that the baseline finish date.