I have a level of effort activity with duration % complete. Cost is assigned to it as material resources price. But the cost is not getting distributed through the duration of the activity. In the profile/spreadsheet, the cost just stays in the start date of the activity. No idea why..
Cost of level of effort activity
Forum Sponsor
Top Posters
Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Thank you..
Thank you..
go to the activity directory then the resource tab right click in the bottom resource window add a column for curve
then assign a curve to the resource