Dear All,
Introduction:
We are preparing for a revised program (Rev.2), the baseline program (Rev.1) already having in-progress activities and will be considered as a baseline for Rev.2 program. The planned dates and planned values to be calculated from the baseline program (Rev.1). So Rev.1 program is assigned as a baseline inside Rev.2 program
Problem:
When I show the Planned Value colum, I am getting a wrong planned value which is based on the planned dates of Rev.1 program while it is supposed to be equal to the Remaining Cost + Actual Cost of Rev.1 program.
Solution Tried:
I have reset the planned dates of Rev.1 program to set it as a baseline for its-self. Unfortunatelly, this is impacting the %complete or the Actual Cost.
Anyone can help on that to get correct Planned value directly from Rev.2 program (with assigned baseline: Rev.1 program)
Regards,
Karim Shaheen
Thanks, yes it is really good solution but when I did it, the %complete have been affected. If I corrected the %complete again the current dates won't match the planned dates. It is like closed loop process.
In Rev 1 prior to save as Rev 2 set planned dates=current dates. After doing so save as Rev 2. Then proceed.