Clause 8.6 calls for a Revised Program to complete the Works within within the Time for Completion.
Here, the Time for Completion has elapsed... True, we need a program to know when the contractor would complete the Works. But can we call this program a 'Revised Program'?
Member for
19 years 10 monthsHi JoseIt is the same thing -
Hi Jose
It is the same thing - He is not going to complete in time so he must issue a "Revised" programme.
Best regards
Mike T.
Member for
18 years 5 monthsThanks Mike for the
Thanks Mike for the reply.
Clause 8.6 calls for a Revised Program to complete the Works within within the Time for Completion.
Here, the Time for Completion has elapsed... True, we need a program to know when the contractor would complete the Works. But can we call this program a 'Revised Program'?
Best Regards,
Jose
Member for
19 years 10 monthsHi Jose - Welcome to Planning
Hi Jose - Welcome to Planning Planet
You do not tell us which of the FIDIC books you are working under but the principle is mostly the same.
This is from the Red Book 1999.
1. Issue a Notice of Non Completion under 8.7 stating that LD's will be deducted.
2. Require a revised Programme under 8.6.
Best regards
Mike Testro