Primaver P6 Performance calculation

S
SAchin GAur 👤 Member for 10 years 1 month

i have one project with baseline & update with percent complete as Physical. I was showing the project progress as Schedule % complete  VS performance % complete.Now i have changed the percent complete as duration.

please tell me how to show the project progress in terms of duration.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

There is always more than one way to skin a cat

another tool thats wil do this for you is project tracker 

Z
Zoltan Palffy 👤 Member for 16 years 10 months

lets say your project started in January and it is now the end of March 

you have baseline with no progress and u have an updated schedule with progress thru March

go to the baseline count the total number of activities lets say it is 100 to get the total number of activities

add a column for number of activities and when you group and sort select show grand totals

now in the baseline filter for activities where the finish date is less than whatever your data date is in your current schedule

in this example filter where finish is less than March 31, 2106 and lets say that the total activities in this filter is 10 so 10/100 is 10% so your planned number of activities to be completed is 10%

now go to your updated schedule (do not include any new activities such as change notices) 

and filter where actual finish is less than DD or March 31, 2016 in our example. Now lets say that the total number of activities completed is 5 so 5/100 is 5%. That means that you are ACTUALLY 5% complete. 

so the planned % complete is 10% and the actual is 5% this is totally based on the number of activities total, planned to be completed by a certain date and the number of activities actually completed by the data date

what you are not getting credit for are activities in progress meaning that they have started but are not yet complete.

so if you wanted to you could change your filters and add another parameter that includes actvities where % complete is within the range if 1 and 99. This wil pick up in progress activities

so your filter in the updated scheudle would be 

filter for any

where actual finish is less than DD or March 31, 2016 

or 

 where % complete is within the range if 1 and 99

S
SAchin GAur 👤 Member for 10 years 1 month

It cant be evaluated as linear % because in the baseline, It wasnt planned to finish 30%(lets say) at the end of 3 months for a 10 month project.

In the beginning the palnned activities are less.

That is why i am facing this problem to show the Planned VS actual with duation % complete.

Provide any other solution please.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

you need to have resources to measure something against

or you can have a summary bar that rolls up the entire schedule 

or you can do it on a linear % complete over time 

lets say you have a project that is 10 months long so based on time after the 3rd month you should be 30% complete.

that would be your planned progress

now your actual progress shows that you are behind schedule by 1 month so now the overall duration of the project is 11 months and you are actually 20% complete

planned 30%

actual 20% 

straight linear based % complete as it relates to time.

or you can use project tracker to give your percentages 

http://www.willmer.co.uk/projecttracker 

 

 

S
SAchin GAur 👤 Member for 10 years 1 month

 i have already change all the physical % cmplete to duration % complete by a global change.

how can i show the project progress (plan vs actual) by duration % complete ?

S
SAchin GAur 👤 Member for 10 years 1 month

 i have already change all the physical % cmplete to duration % complete by a global change.

how can i show the project progress (plan vs actual) by duration % complete ?

Z
Zoltan Palffy 👤 Member for 16 years 10 months

run a global change

where

physical % complete is greather than 0

then

duration % complete = physical % complete

 

 

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts