Sukumaran Subaramaniyan 👤 Member for 21 years 3 months

Use some imaginary resources to recalculate the required duration to complete the job.



Example : if you need to start some activities concurrently to mitigate the delay, highlight to your project team the necessity to add in more resources to expedite the job.

With this additional resources work out the schedule and inform them the possible new completion date.



Regards.

Z
Zhang Haixiang 👤 Member for 21 years 1 month

Hi,

what do you mean "I could not able to exactly reorganise my schedule".

delay is normal in project,trace the logic of your schedule,especially the critical path to find out what cause the delay,take corrective action if needed.



See what will happen next time you update the schedule

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts