Problem with importing update to the baseline.

A
ahmed samir 👤 Member for 10 years 2 months

hey there,

i face a problem while i'm importing update to the baseline, the progress percentage for all activities wasn't the same in site so i changed all Performance % Complete, Start date and Finish date for all activities, there were some activities in the site completed and in the Xer file is still have % or with Zero %...and some activties percentages got increased and some got decreased...

when i prepared the Excel sheet and import it to baseline to re-update everything from the begining, the baseline didn't change and everything still Zero.

 

anyone have a solution for this problem ??

 

Regards, 

M
Muhammad Bilal 👤 Member for 11 years 1 month
All Members Good Day.
I am facing one problem which is i made Rev-05 of my In-Progress Project in which i added one Activity given Relationships to some other activities. I made the Rev-05 by Restoring the Baseline. Now when i assigned this Latest Baseline to Updated Progressed Schedule, the added new Activity is not shown. Please let me help out. How can i Show effectively the added activity in the new baseline with Actual Progress Schedule.
Thanks
Z
Zoltan Palffy 👤 Member for 16 years 10 months

make sure that your duraiton type is fixed duration & units/time

run a global change 

where performance % complete is not equal to 0

then

duration % complete equals performance % complete

and importing for progress MUST have start TIMES for activities with actual starts and must have start and fnish TIMES for activities with actual starts and finishes

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts