hi,
Mobilization duration is 4 months.,
can i take it as Milestone or activity?
This can sound silly question .
Regards,
Vigeeth
hi,
Mobilization duration is 4 months.,
can i take it as Milestone or activity?
This can sound silly question .
Regards,
Vigeeth
you can do it as Tom suggested make it an activity with a 4 month duration however some scheduling specifications will not let you have activities that long in duraiton over 20 days (except for procurement activities). So you can break it down into 4 sperate activites Phase 1 mobilization 20 days, Phase 2 mobilization 20 days, Phase 3 mobilization 20 days and Phase 4 mobilization 20 days.
or Pre mobilization 20 days, Start mobilization 20 days, continued mobilization 20 days, finish mobilization 20 days.
that will get you your 4 months you can also a a milestone at the beginning and or end of this chain if you would like.