Milestone

hi,

Mobilization duration is 4 months.,

can i take it as Milestone or activity?

 

This can sound silly question .

Regards,

 

Vigeeth

Z
Zoltan Palffy 👤 Member for 16 years 10 months

you can do it as Tom suggested make it an activity with a 4 month duration however some scheduling specifications will not let you have activities that long in duraiton over 20 days (except for procurement activities). So you can break it down into 4 sperate  activites Phase 1 mobilization 20 days, Phase 2 mobilization 20 days, Phase 3 mobilization 20 days and Phase 4 mobilization 20 days.

or Pre mobilization 20 days, Start mobilization 20 days, continued mobilization 20 days, finish mobilization 20 days.

 

that will get you your 4 months you can also a a milestone at the beginning and or end of this chain if you would like. 

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts