Resource, Assignments, Sorting

In P6 15.2 web client, in the "Resources" tab, then in "Assignments", I am grouping my level 1 by Project name, and then I want to sort the level 1 project groups by date.  What P6 wants to do is sort my tasks inside each project by date, but I want to sort each project by date.  Any thoughts on how to do this?  Thanks!

W
Will Radford 👤 Member for 10 years 9 months

Raymund, thanks for the reply, but if i group level 1 by start and level 2 by project I don't get what i need because I will have different tasks from the same projects scattered throughout the list.  I want to group the project first to keep all related project tasks together, and then get a chronological order of the projects.

W
Will Radford 👤 Member for 10 years 9 months

Raymund, thanks for the reply, but if i group level 1 by start and level 2 by project I don't get what i need because I will have different tasks from the same projects scattered throughout the list.  I want to group the project first to keep all related project tasks together, and then get a chronological order of the projects.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts