Hello Planners,
is it possible to convert Activity Code into WBS entries? I have tried to write a Global Change saying "WBS = ", but the value can only be one of my WBS nodes.
Thank you,
Alexandre
Hello Planners,
is it possible to convert Activity Code into WBS entries? I have tried to write a Global Change saying "WBS = ", but the value can only be one of my WBS nodes.
Thank you,
Alexandre
I have used the sdk excel workshet with version 6.2 and it works fne. In the spreadsheet the first column must be the wbs number in its entirety, The second column is its parent number or one number less than the number in the first colum. The third column is the last number in the first column. The fourth column is the description of the WBS. I have added over 600 wbs elements using the spreadsheet and it worked fine.
Does SDK still work, we thought the service was stopped after version 8.
On the query, one of the option would be to group by codes, create WBS as required. Display WBS column and use fill function.
Thank you all,
Alexandre
You can group your codes the way that you want them then summarize your activities and roll them up. You can use this information to create your wbs structure.
You can copy this info to excel then use the wbs excel using sdk to create your wbs structure.
Or you can print the summary and manually enter it in the wbs structure.
or you can use this method with the exel file parser
https://www.planacademy.com/using-primaveras-xer-file-parser-import-wbs…
Suggests to use the Import / Export Excel through SDK.