Indicator of ressource assignment

P
Phil Gab 👤 Member for 10 years 3 months

Hello all, 

I am new to this forum.

I would like to create in the table of my Gantt Chart an indicator showing if one or more resource is assigned to the task (ie green light if any resource, red if none).

i am trying to use a custom field indicator but it does not work.

Exemple : i am trying to check if the field [Resource name] is Null or not.

Any idea how to do ? 

Thanks.

P
Phil Gab 👤 Member for 10 years 3 months

Hi Tom, 

I figured it out yesterday.

IIf([Noms ressources]<>"";Oui;Non)

It works well, i do not know what i have done before ...

Thanks !

T
Tom Boyle 👤 Member for 19 years 6 months

Hi Phil, Maybe you have a typo in the field name.  This works for me in a custom Flag field: IIf([Resource Names]="","No","Yes").  Then green and red stoplights based on the flag value.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts