Resource Limitation/Restriction in Primavera

I
Irfan Khan 👤 Member for 16 years 10 months

example.jpg

Z
Zoltan Palffy 👤 Member for 16 years 10 months

this depends on your logic if Activity A, B & C have Start to Start relationship with one crew and Activity D, E & F have Start to Start relationship with the same crew thne make activity D a successor to activity A and make E a successor to activity B and make activity F a successor to activity C or make D a successor to activity A all with FS relationships.

W
wang chao 👤 Member for 15 years 2 months

Actually it is the workflow function, I think this is can't automatic generate (depending on the current reviosn function) .It only can be found by manual.

R
Raymund de Laza 👤 Member for 16 years 6 months

After Setting my suggestions... run Resource Levelling with priorities.

Hope this will help.

I
Irfan Khan 👤 Member for 16 years 10 months

Thaks Mr. Raymund for your reply,

 

Settting MAX Unit/Time is not solving my problem, let me explain you again that :

I have only one crew which is working parellay with 1st group of activities i.e. activity A, B & C, second part is that my activties D, E & F will start just completion of activity A, B & C. 

 

all activities has assigned one crew only which will work only when my Group 1 Activities will finish, therefore i am wondering an option whcihc will stop me to start any activity in group to unless all of actvities finish in Group 1.

 

Hope you understand what i am looking for.

 

thanks.....

R
Raymund de Laza 👤 Member for 16 years 6 months

Set the MAX Unit/Time for the Crew in the resource Pane. In your example the MAX unit is 3 Multiplied by Working Time for the crew per day. Say your crew will work 8hrs per day then your MAX will be 24hrs/day.

Hope this will help

I
Irfan Khan 👤 Member for 16 years 10 months

Hi to all Experts,

 

I was wondering that how to manage my limited resources through Primavera P6.

 

If the Case is like that :

 

I have 6 activities 

Activity A

Activity B

Activity C

Activity D

Activity E

Activity F

Actually, Activity A B & C having Start to Start relationship with one crew and i have only one crew which will perform its job after completion of 1st group of 3 activiteis. Furthermore, the successor of Activity C is the Activity D & than linke to Activity E & F with Start to Start relationship. 

the question is, how can i prevent activity D for being actualized unless my Activities of group 1 didnot finish its job, becasue i have one crew only in order to perform after completion of Group 1.

hence, i want restriction on activities with the help of due to limited resource.

Hope i everything is clear here, for more information please see the snap shot.

thanks...... :)

 

 

 

 

I
Irfan Khan 👤 Member for 16 years 10 months

Hi to all Experts,

 

I was wondering that how to manage my limited resources through Primavera P6.

 

If the Case is like that :

 

I have 6 activities 

Activity A

Activity B

Activity C

Activity D

Activity E

Activity F

Actually, Activity A B & C having Start to Start relationship with one crew and i have only one crew which will perform its job after completion of 1st group of 3 activiteis. Furthermore, the successor of Activity C is the Activity D & than linke to Activity E & F with Start to Start relationship. 

the question is, how can i prevent activity D for being actualized unless my Activities of group 1 didnot finish its job, becasue i have one crew only in order to perform after completion of Group 1.

hence, i want restriction on activities with the help of due to limited resource.

Hope i everything is clear here, for more information please see the snap shot.

thanks...... :)

 

 

 

 

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts