you wil also want to change your data date to equal your start date
Dear Shawkat,
You can chnage/Modify your start date @ anytime by following these steps :
1 - open your project & go to Project Window
2 - Click on Date Tab
3 - You can see there an option "Project Planned Start" just change it to your desired date you want.
hope this will help