Duartion and Units

N
nicki green 👤 Member for 10 years 4 months

Hi there,

 

Am i right in thinking that in order to get the duration and labout units the same, the duration type should be set at "fixed duration and units/time"?

I want the duration to read the same as the labour units.

Thanks

 

Nicki

Z
Zoltan Palffy 👤 Member for 16 years 10 months

1st make the default units/time for the resource equal to 1 then set the duration type to fixedunits/time then add the resource 

whatever you make the budgeted unts will make the duration the same 