Percentage complete

Hi all

Ill give you a scenario.

i have an activity which has 800 man hours budgeted for it and say i have done 400 hours is there any way i can add the hours in so it will change the physical % complete automaticly?

 

Sorry for the simple questions im new to this game.

 

regards

 

L8S