Vignesh S 👤 Member for 11 years 2 months

In the project which I am working on, most of the activities have more than one predecessor/successor links(usually 5+). Also, no. of activities is 1000+. If I link all of them, the time-distance view looks much clumsy and there is no clarity of schedule presentation. But, none of the links are avoidable as it will affect the dpendency logic behind the schedule and future updation of the schedule will also be a cumbersome one. Is there any option available to make some of the link lines invisible.???

V
Vignesh S 👤 Member for 11 years 2 months

Alexandre,

Thanks for the nice suggestion and this works well as per my requirement.

Vignesh

A
Alexandre Faulx-Briole 👤 Member for 23 years 6 months

Hello Vignesh,

Try by selecting different layers for the links you want to display and the others; select the link and open the properties box, you will find the "Layer" field

Alexandre

Featured Partner

Top Posters

Pan
0 posts
Tijo Kurian
11 posts
Zainab El-Beialy
3 posts
Kamlesh Parmessur
4 posts
MR JUDE C ANYAEGBU
0 posts
GeoVe
0 posts
Ashkan Mohammadi
0 posts
Jeroen De Bauw
0 posts
Senior Planning Engineer
0 posts
Kristian Mcwilliams
1 posts