Primavera P6 wandering Baselines

R
Rachel Lowe 👤 Member for 14 years 10 months

Hello, I was just wondering if anyone could help me.  I am working on a number of programmes / schedules within Primavera P6.  All of which have baselines.  I have set the Project and Primary baselines within 'Assign Baselines', but every now and then when I return to the programme to run a filter or print, the baselines have re set back to >Current Schedule> for the Primary baseline or selected an alternative / old baseline for the project baseline.  Has anyone any idea why it does this or if there is something I am missing / doing wrong.  It doesn't do it every time I access the programme, sometimes it is as I left it.

 

Many thanks

R
Rachel Lowe 👤 Member for 14 years 10 months

Ok, thank you.  I'm not a super user, but I will speak to the superuser that I work with and see if they can do anything.

 

Many thanks

R
Raymund de Laza 👤 Member for 16 years 6 months

Hi... the issue is with the database. If you are a poweruser create a new username then use it to login. Hope this will help.

R
Rachel Lowe 👤 Member for 14 years 10 months

Thanks for your reply, Zoltan, unfortunately that's what I'm already doing and it still keeps occasionally changing the baselines.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

when you select assign baseline make sure to select the baseline for the Project Baseline as well as the Primary Baseline

also whenever you exit the program make sure to select file close all lthen file exit 

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts