I'm very new to P6 therefore apologies for any 'stupid' questions I might be asking over the course of time until I get up to speed.
I'm currently pulling together a programme (I work on rail projects) that consists of a lot of surveying works which range over a period of saturday nights or some days one week, then a few more days a couple of weeks later. How do I show a task that is split over a period of time?
Also, can I colour code the bars to show what activties are dayshift, nightshift etc?
Any advice most welcome.
Thanks.
D
Thanks...I'll have a look at this and try and sus it out and let you know how I get on :)
Hi,
Use Bar Necking for Splitting of Bar, create a separate calendar for the specific activity.
For the Color Coding, use activity codes to specify colors for different bars.
Hope this will help.