Hello everybody,
I am searching an answer for showing ordinal dates instead of ceartain dates but I couldn' t find a specific way. My problem is the project start date is not certain and I want to show the dates as ordinal dates, like to day 1, 2 etc instead of 25 dec, etc.
At columns part I want to show ordinal date instead of BL project start - end.
I will appreciate if someone can help me,
Thanks & regards,
Ufuk
Ufuk,
Follow the steps below.
[[wysiwyg_imageupload:3208:]]
[[wysiwyg_imageupload:3209:]]
[[wysiwyg_imageupload:3211:]]
[[wysiwyg_imageupload:3212:]]
=jerome
These data do not appear at my primavera (P6 R8.3.2), still couldn' t find a way for this ...
These data do not appear at my primavera (P6 R8.3.2), still couldn' t find a way for this ...
Under Global Change, you should find these fields under the "Then" section parameter. See attached screenshots.
[[wysiwyg_imageupload:3206:]]
[[wysiwyg_imageupload:3207:]]
I have tried, I checked my primavera but couldn' t see any "user_start_date1" or "user_integer1" etc. How can we create these.
Thank you,
Hi,
Have you tried response #3 from this thread?
http://www.planningplanet.com/forums/primavera-version-pm5-pm6/420500/displaying-es-and-ef-day-number-instead-date
Amro thanks for your answer, there was ordinal dates column available at previous versions but it is not available at the latest version, I guess. I can hide the dates columns but I have to show ordinal days ...
Amro thanks for your answer, there was ordinal dates column available at previous versions but it is not available at the latest version, I guess. I can hide the dates columns but I have to show ordinal days ...
Hi,
my suggestion to you to show in Gantt chart and just hide colums of dates on activity table .
Because in User Preference this not available option.
Thanks