Assigning resources from BL to update

Dear All

I finished base line 

Then i made update, all this without assigning resources.

Then consultant asked me to assign resources, I did for the baseline.

now there is a way to make update again to resources BL , but because

I changed many relationships I want to know if there a way to move assignments from the BL to the update ?

Thanks in advance

 

A
Abilash Palakkadan Mathew 👤 Member for 13 years 9 months

The whole current schedule can be updated to BL by update the baseline option. But I prefer not to do that. If i was there at your situation i will set the current file as a new baseline and assign this new BL to current schedule to monitor furthed. If required i will be available on 00971563911927

M
mohamed abdalgawad 👤 Member for 14 years 6 months

Thanks very much for response but may be i didn't make myself clear;

I will ask anothe question:

can i import relationships from update to BL ?

A
Abilash Palakkadan Mathew 👤 Member for 13 years 9 months

Please do following steps

Make a copy of baseline file
Restore that baseline copy file
Import the resource assigments into the restored file
Assign this file back as the baseline

By
Abilash

A
Abilash Palakkadan Mathew 👤 Member for 13 years 9 months

Please do following steps

1. Make a copy of baseline file
2. Restore that baseline copy file
3. Import the resource assigments into the restored file
4. Assign this file back as the baseline

By
Abilash

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts