For the Activity schedule and the resource loading is it required to included the hours or percentage for the weather factor.
Regards
Dear All,
For the Activity schedule and the resource loading is it required to included the hours or percentage for the weather factor.
Regards
that depends on the specifications but regardless I would certainly include both.
I would create an anticipated adverse weather in my calendar and assign my exterior work activities to this calendar.
I would also add resource to my schedule so that you can track the required budgeted manpower as well as the actual manpower on the project.
https://www.linkedin.com/pulse/new-aace-recommended-practice-adverse-we…;
http://www.aacei.org/toc/toc_84R-13.pdf
Good Luck