Problem with resource after reinstalation. P6 'stand alone'

Good evening to All.



I work on "stand alone" version of P6. After reinstalation i have problems with resources.



I have created for my schedule labour resource with "default units per time" = 99/day. I have assigned it for few activities, put a number of budgeted units and I have started to schedule. It was ok. Everything was going just well. We were measuring progress of our project using this units.



...but...



After reinstalation of P6 when I opened my schedule, budgeted units for this activities were changed. The same with "default units per time" =9/d (?).



I don't have any idea what have happend. Maybe somebody had some similar problems with importing xer after reinstalation.



I will be grateful for any feedback.

taras83

P
Piotr Tarasiewicz 👤 Member for 10 years 7 months

Admin was testing settings on my stand alone version. I've already had conversation with him...

Z
Zoltan Palffy 👤 Member for 16 years 10 months

which begs the question why were the setting different in the 1st installation vs the 2nd installation

P
Piotr Tarasiewicz 👤 Member for 10 years 7 months

Yes of course.

I've done some research and found solution.

Issues was concerning to "Multiple resource assignment" in "User preferences panel".



After re-installation some options have been changed. One of them was "Resources Assignment". After restoring settings and user preferences everything is just fine.

Thank you for your effort.

[[wysiwyg_imageupload:2880:]]



pt

Z
Zoltan Palffy 👤 Member for 16 years 10 months

i assume that you exported the file prior to reinstalling p6  ? Then imported it back into p6 after it was reinstalled ?

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts