Hi to all! I am a bit confused regarding default units/time for any resource matreial specially concrete.Somebody informed me that put ZERO in default units/time in any material resource and after doing this the budgeted units also become zero.Please suggest or guide me what is the correct thing in any Material resource case in P6.
Material resource Default units/time
Forum Sponsor
Top Posters
Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
yes when you go to leveling near middle make sure that Level Resources only when activity total float box is checked and that below it that Preserve minimum float when leveling is 0
Dear Sir Zoltan
Actually i need to level resources within the limit of end date of my project
is it possible?
I am not sure what you expected but thats what leveling does
Dear Sir Zoltan
thanks for the reply
I have chosen Option#3 Level resources but this option pushed my schedule 10 months forward..
you have three options
option #1
change your logi and make more of the relationships FS
option #2
increase your durations to use less manpower and spread it out more
option #3
use the leveling too
tools level resource then choose what and how you want to level your resources
Dear Sir Zoltan
what is the procedure of levelling resources in p6?it seems i have over allocated my resources in the schedule..Please help
Thanks in Advance
Umair
I do not use P6 but recall its updating is awkward with regard to time phased data and required you to make periods updates based on fixed periods so fixing previous periods performance can be a nightmare.
The database of the software I use allows you to delete specific prior period event updates and create new ones for prior periods for an easy fix of the table. It does not require fixing Financial Periods to get the right time distribution because of superior algorithm to calculate the distribution for any period of your choice. I do not believe you can do this with P6.
The operation to fix past performance events in Spider Project is very simple; it is similar to the regular updating procedure wich requires only steps 2 and 3.
In this way your Performance Archive Table is fixed and your time phased reports [including EVM reports] will be correct. This procedure is also convenient when new activities are added and these activities have some progress before current DD.
Going back in time to a prior version and fix the data by running several updates along with period performance is insane, just imagine a small error is still to be fixed, what a mess it would be. I suppose for P6 there shall be a better way than going back to a previous version and run again periods updates with the settings fixed as per your recommendation. The P6 way to fix prior periods performance I do not know.
I also recall P6 having issues when the Financial Periods among jobs is different as it only allows for a single definition. Some users were recommending using a separate database for each client but what happen when different units of the same client use different financial periods?
so what was the ultimate solution
Its done guys thanks for your support and help
- Better yet delete the exiting resource and create a NEW resource with the default units/time NOT equal to zero then add the resource again.
No problem dear brother Zoltan..
Thanks for guiding me
if you followed what I have written it should work go back thru the instructions again.
Better yet delete the exiting resource and create a NEW resource with the default units/time NOT equal to zero then add the resource again.
Sorry I can not do you work for you. I can only guide you.
Dear Zoltan
I have followed every step according to your instructions but still no results.Can you do me a favour actually i want to share my schedule with you via email so you can check where am i doing mistake.So,if you dont mind give me your email address i will send my schedule to you and this will be a big help for me because then i can submit my plan to my boss.
Thanks in Advance..
filter for all activities
add a column expand percent completes and choose percent complete type
make the 1st one physical % complete
do a fill down in this column and make them ALL physical % complete
go to projects directory make sure your project is highlighted
click on the defaults tab
change duration type to percent complete type to physical
Your image show that the Percent complete type is Duration. Change to Physical as Zoltan suggests.
Dear Zoltan I have checked the admin preferences and also my duration is physical percent complete but earned value costs and planned value costs are still not showing.Is there any other reason for not showing the earnes and planned costs?I am also enclosing XER file for you..Thanks in Advance
Zoltan,
I did not understand your explanation.
It is clear for labor resource but the question was on material resource.
What is unit/time for material resource and why it is 1?
Besides dividing by zero does not provide zero.
make sure that you are using physical % complete and also go to admin preferences
click on the earned value tab
make sure that the technique beiing use is activity % complete
and make sure that ETC calculations is set to ETC = Remaining cost for activity
Dear Zoltan
I am having another issue in my project plan i.e earned value costs and planned value costs are not showing while earned labour units and planned labour units are showing.I have entered the every resource cost and its also showing the costs against every activity on the main screen.Can you please help me why Earned and planned value costs are not showing at the time of generating report from the p6?
Thanks in advance
no problem
thanks for the help zoltan..
for material default unit/time use 1 because any thing divided by zero or multiplied by zero is what ? Yes zero
so what it does is basically is multiplying the default units/time by the duration to get the budget amount and for distribution it is dividing this budget amount duration and is spreading this amount units/time by the start and end date of the activity. So multiplying and or divided anything by zero will be zero.
for example if you have a resource for labor and set the default units/time to be 8 and you have a duration of 5 days it will take the 5 days time 8 hours per day 5*8=40 budgeted units. Then for the distribution it will spread the 40 hours by the units/time in this case 8 so it will show 8 hours per day for 5 days.