Progress percentage and scope of work

S
Sunil Babu 👤 Member for 15 years 6 months

Dear All,

The case scenario of the Project is like this :

After completion of gradeslab client removed the scope of the building and given to another contractor.

My question is Option A: Upto that instance can we put the remaining works of that building as 100% complete, or option B we have to revise the Baseline by removing the remaining activities of that Building and re-shedule which option will give better result on account of project progress.

Expert remarks will be highly appreciable.

With Best Regards,

Sunil.

S
SAADI karim 👤 Member for 10 years 8 months

Dear Sunil.

       I thing is better to remove the remaining tasks regarding the building and get the new baseline and do analysing what you have to complete.

 

 

Cheer

SAADI 

G
Gary Whitehead 👤 Member for 17 years 2 months

It depends on what your contract says.

 

Some contract forms have no mechanism for a change in scope to bring the contractual completion date forward, some do.

Some contracts require a project to be re-baselined with every major contract variation,some don't.

Read your contract and/or check with your contract manager

 

If this is not a contractual issue, and you are talking about an internal baseline purely used to mintor project progress rather than manage the contract, then re-baselining will give you a more accurate measure of project progress.

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts